Project Overview
The structure of the East hall of the Capital Museum is divided into two single buildings, the main building and the shared hall. The two buildings are connected by the underground exhibition corridor and the steel structure corridor on the ground. The corridor adopts sliding support to make the two monomer ground parts completely detached.
The steel structure of the shared hall and corridor is composed of the underground rigid structure, the above-ground box steel column, the special-shaped column and the roof analysis frame. The roof analysis frame adopts the inverted triangle arc pipe analysis frame structure, the north side is 145.2m, the south side is 192.3m. The roof of the shared hall as a whole is high in the south and low in the north, high in the east and west ends, and low in the middle. The highest elevation is 25.200m, and the overhang is 9m on the north side and 4.5m on the south side. The maximum span of the roof frame is 40m, and the height difference between the north and the south is about 11m. The corridor is mainly composed of analysis frame structure.
The main section forms of the shared hall and corridor include round tube, welded box, shuttle, H-shaped section, etc. The maximum plate thickness is 50mm. Materials include Q345B, Q345C, Q355B, Q390B.
Technical Features
Compared with the conventional steel structure installation method, the construction of ultra-long inverted triangle curved pipe truss has the following characteristics.
The super long truss is a curved inverted triangle truss, the truss is processed as a whole in the processing plant, the truss assembly and pre-assembly are combined, according to the transportation capacity, the segment transport to the site after the assembly of the whole lifting, effectively solving the problem of segmented lifting or high-altitude bulk, the chord and the belly bar of the space Angle, and the extremely difficult high-altitude butt.
According to the characteristics of the large installation height difference between the two ends of the truss, the special design of the ball hinge support is made. After the low support is anchored, it is directly welded with the truss and steel column, while the high support is anchored and temporary connecting bolts are designed. During the installation, the support is bolted, so that the support can not only release the construction deformation, but also meet the need for no deformation before the whole support is stressed. After the overall installation is completed, the high support is welded, and the anchoring device of the high and low support is removed.
According to the height difference of the installed position of the truss, two lifting points of the steel wire rope and the high point of the truss are designed. The two lifting points of the low point of the truss are directly lifted by the steel wire rope. The steel wire rope is connected by two manual hoists, and then the lifting ear plate is connected by the shackle. Before hoisting and positioning, the height difference of the component should be adjusted to the predetermined Angle, and the position of the lifting point should be accurately calculated.
The assembly site should be smooth and solid, and the assembly tire frame should be set in the same position as the assembly tire frame in the processing plant, so as to restore the pre-assembly conditions of the factory to the maximum extent and effectively ensure the assembly accuracy.
The subgrade boxes are laid on the weak foundation of the crane working area, and the reinforcement design is carried out. All subgrade boxes are covered horizontally, and the subgrade boxes are connected as a whole by temporary connecting plates.
The method of laying subgrade box to strengthen the foundation effectively solves the problem that the large crawler crane is weak in the backfill pavement.
Process principle and flow
According to the mechanical characteristics of the whole steel roof, the overall size of the truss is long, the span is large, the height difference between the two ends of the single truss is large, the truss and the steel column are connected by the ball hinge support, the lateral force is large during the installation of the truss, and the concrete structure under the truss is complex, and the main roof of one side has been lifted, and there is no crane standing conditions.
This requires that only a unilateral site can be selected as the lifting surface during the construction process. During the construction process, the truss itself is stable and cannot move sideways. There should be enough deformation capacity to release the stress, and before the truss and the connected beam are stressed as a whole, the support can not be displaced, rotated and other deformation.
A large crawler crane is used to design the truss support node, pre-anchor the ball hinge support, and design the high point support as a temporary bolt, so that the stress and strain are released smoothly, and ensure that the whole support does not displace before the load, to ensure the integrity of the structure, improve the construction speed, greatly shorten the construction period, and ensure the quality and safety of the project.
Super long inverted triangle arc pipe truss overall lifting construction process: Processing and production of trusses → field investigation and data collection → measuring and setting off → handling of hoisting work surface → Approach of large crawler crane → Installation of steel columns → Installation of supports → assembly and welding of trusses on the ground → overall hoisting of trusses and welding of supports → Hoisting of the second trusses → Hoisting of connecting beams between trusses → Hoisting of the next unit → overall roof installation completed.
Technical points for the overall installation
4.1 Truss processing
The trusses are assembled into trusses by a single rod as a whole in the processing workshop, and the whole trusses are used as a group of processing units. After the overall processing is completed, they are split according to the transportation length and shipped to the site.
This processing scheme is equivalent to the combination of workshop assembly and pre-assembly to ensure the accuracy of the on-site truss docking.
(1) Steel pipe bending arc. The steel pipe is curved by special hydraulic equipment, and most of the steel pipe is cold-pressed. If the diameter and thickness of the steel pipe are relatively small and the cold-pressed base material is easy to crack, hot pressing is used.
(2) steel pipe intersecting line cutting. The intersecting line of the belly bar is cut on the special intersecting line cutting equipment.
(3) Truss assembly. Trusses are designed in the processing workshop for special assembly tire frames and assembled in sections as a whole. After assembly, it is divided into transport sections, entered the painting workshop, sandblasted to remove rust, sprayed primer and intermediate paint, and then transported to the site.
(4) Because the roof truss is extremely long, the truss is segmented according to the transportation length, and each section does not exceed 18m.
(5) The size of the truss and the pre-arch value of the truss should be controlled during on-site assembly, and the pre-arch value should reach L /500, that is, 107mm, according to the requirements of the deepened design instructions.
4.2 Field investigation and data collection
(1) The data should be available before the construction of the truss: the foundation bearing capacity report of the hoisting operation area; The steel column is welded, the steel column connecting beam is welded, and the weld seam is qualified; Measuring baseline and level point data; Engineering design related documents.
(2) Timely remove obstacles on the ground of the crawler crane working surface.
(3) The construction site should be basically flat, and the ground endurance should meet the requirements of equipment walking.
(4) There should be enough assembly site, and the ground endurance of the assembly site should meet the requirements.
4.3 Measuring and paying off cables
Before construction, according to the design drawing and coordinate reference point, the spindle column support, especially the coordinate of the pin hole of the steel bracket, is precisely calculated, and the coordinate data is checked. Using measuring instruments to lofting, notify the relevant units for pay-off review.
(1) During the hoisting period, use the total station to track and measure the whole process.
(2) After the completion of lifting of single components, retest the installed components in time.
4.4 Handling of hoisting surfaces
(1) The crawler crane walking area is the original excavation bridleway or backfill soil, the local slope is large, the bridleway surface is smooth and compacting, and is covered with steel plates, and drainage facilities are set.
(2) The ground of the crawler crane walking area is covered with roadbed boxes, the roadbed box specifications are 2m×6m, and the track contact length with the ground is 8.7m. According to the calculation of 10 roadbed boxes bearing the lower part of the two tracks, the contact area between the roadbed box and the soil is 120m2. According to the crawler crane's self-weight of about 400t, for example, with load and considering the dynamic coefficient of about 480t, the foundation bearing capacity is required to be about 40kPa.
Considering that the main arm is vertical to the crawler during lifting, the limit value of unilateral crawler is 80kPa, and the bearing capacity of the foundation of the crawler crane walking route is 96kPa.
4.5 Large crawler crane approach assembly
Crawler crane adopts the main arm + auxiliary arm condition. The crawler crane parts enter the field and are assembled by the equipment manufacturer. A relatively flat site of 100m length and 10m width is required for assembly.
4.6 Steel Column Installation
(1) The steel column is hoisted by crawler crane.
(2) After the steel column hoisting is completed, the steel beam connecting the steel column is hoisted.
(3) After the correction, welding and inspection of steel column and steel beam are completed, prepare to lift the truss support.
4.7 Support Installation
(1) The support adopts cast steel ball hinge support.
(2) The temporary anchoring device is welded before the low zone ball hinge support leaves the factory, and is welded directly with the steel column after installation.
(3) In addition to welding the temporary anchorage device, 4 long round hole ear plates are also needed to be welded before the high zone ball hinge supports are delivered. During the installation of the supports, they are not welded with the steel column temporarily, but are only bolted at the ear plates to ensure that the support can be dislodged in a small range as a whole.
(4) After the overall installation of the truss and connecting beam is completed, weld the high support, remove the long hole lug plate, and cut the support anchor device.
4.8 Truss floor assembly
(1) The assembly length of the truss ground should be solid and basically flat, and the steel plate should be padded in the weak part of the site, and the elevation should be adjusted by assembling the tire frame.
(2) The design position of the truss assembly tire frame should be consistent with the design position of the segment tire frame in the processing plant, and the pre-assembly conditions of the factory should be restored to the maximum extent to ensure the assembly quality.
(3) After the on-site assembly of the truss is completed, the interface is welded and the flaw detection is completed.
4.9 Truss overall lifting and welding
(1) Select the hoisting wire rope and shackle according to the weight of the truss, as shown in Figure 1.

Figure 1 Single roof truss hoisting elevation
(2) Software should be used to calculate and analyze the location of the lifting point of the truss. Taking the truss of the shared hall of the East Hall of the Capital Museum as an example (Figure 2), the distance between the left end of the lifting point and the side of the rope is 13.3m, and the distance between the right end of the rope and the right end is 14m; The center of gravity of the component is 26.2m from the left end and 26.8m from the right end; The left side length of the wire rope is 15.8m, the right side length is 18.6m; The Angle is 45 degrees. The maximum stress is 48.90MPa.

FIG. 2 Stress cloud map
According to the above calculation results, the deformation of the cantilever end in the hoisting process is 20.76mm.
Closing remarks
The use of truss integral lifting technology effectively reduces the field altitude docking, realizes the field truss chord zero deviation docking, the overall installation deviation is less than the specification requirements.
By decomposing the key line construction period to the non-key line assembled on the ground, the construction period is saved by 20d, the mechanical cost and labor cost are saved by 1.1 million yuan, and the economic benefits are obvious, which has a good reference for the construction of similar projects.